What are Gantt charts?

An overview of Gantt charts and how they can help manage agile projects.

Eddie Meardon By Eddie Meardon
Browse topics

Summary: A Gantt chart is a project management tool that illustrates work completed over a period of time in relation to the time planned for the work. A Gantt chart can include the start and end dates of tasks, milestones, dependencies between tasks, assignees, and more.

In the early part of the 20th century, Henry Gantt created charts that recorded the progress of workers to a task. It allowed supervisors to quickly see if production schedules were behind, ahead, or on track. Gantt charts revolutionized project management, helping to manage large construction projects like the Hoover Dam and the interstate highway network. While Gantt charts were initially written out on pieces of paper, with the rise of computers in the 1980s, Gantt charts became increasingly complex and elaborate. Today, Gantt charts are still one of the most widely used project management tools.

What is a Gantt chart?

A Gantt chart is a project management tool that illustrates work completed over a period of time in relation to the time planned for the work. It typically includes two sections: the left side outlines a list of tasks, while the right side has a timeline with schedule bars that visualize work. The Gantt chart can also include the start and end dates of tasks, milestones, dependencies between tasks, and assignees.

Today, Gantt chart tools are often referred to as roadmap tools. To keep up with the demands of modern software development, roadmap tools like Jira Software include features like a collapsible task structure and resource management panels. This helps teams maintain a coherent project strategy despite the iterative nature of the software development process. Jira includes two roadmap tools to create Gantt charts for your projects: Roadmaps, which creates plans around Jira issues assigned to a team, and Advanced Roadmaps, which does the same thing across teams and organizations.

Screenshot of Jira Basic Roadmaps

Roadmaps

Screenshot of Jira Advanced Roadmaps

Advanced Roadmaps

What is a Gantt chart used for?

Project managers use Gantt charts for three main reasons:

Build and manage a comprehensive project

Gantt charts visualize the building blocks of a project and organize it into smaller, more manageable tasks. The resulting small tasks are scheduled on the Gantt chart's timeline, along with dependencies between tasks, assignees, and milestones.

Determine logistics and task dependencies

Gantt charts can be employed to keep an eye on the logistics of a project. Task dependencies ensure that a new task can only start once another task is completed. If a task is delayed (it happens to the best of us), then dependent issues are automatically rescheduled. This can be especially useful when planning in a multi-team environment.

Monitor progress of a project

As teams log time towards issues in your plan, you can monitor the health of your projects and make adjustments as necessary. Your Gantt chart can include release dates, milestones, or other important metrics to track your project’s progress.

The benefits of using a Gantt chart

There are two main reasons Gantt charts are loved throughout the project management world. They make it easier to create complicated plans, especially those that involve multiple teams and changing deadlines. Gantt charts help teams to plan work around deadlines and properly allocate resources.

Project planners also use Gantt charts to maintain a bird’s eye view of projects. They depict, among other things, the relationship between the start and end dates of tasks, milestones, and dependent tasks. Modern Gantt chart programs such as Jira Software with Roadmaps and Advanced Roadmaps synthesize information and illustrate how choices impact deadlines.

Gantt charts in waterfall vs. agile planning

Whether you like the waterfall or agile methodology, Gantt charts can be a powerful tool for either.

Waterfall and Gantt charts

The waterfall model of project planning follows a linear approach where stakeholder and customer requirements are collected at the beginning of the project. From that, project managers create a sequential project plan, complete with milestones and deadlines. Every piece of the project relies on the completion of preceding tasks. This is favored by teams that focus on process (such as construction or manufacturing) and less on ideation or problem-solving as the steps need to be planned out in advance.

Gantt charts are typically preferred by project managers using waterfall. They determine a project schedule by breaking projects into manageable chunks of work and assigning start and end dates. It’s also helpful in identifying important milestones in your project. Milestones are accomplishments that teams should achieve on or ahead of schedule. They are optional but recommended.

Agile and Gantt charts

On the other hand, the agile model of project planning values flexibility and adaptability. Instead of creating a full timeline with set dates, agile teams break projects into smaller iterations (also known as sprints). At the beginning of a sprint, a team plans their work against the goals of the project over the course of the next two weeks. Once that sprint is over, the accomplishments and developments from it help to create the plan for the next sprint.

A Gantt chart can show how changing one task has the potential to impact the plan or the product roadmap. For agile teams, this is essential since stakeholder feedback is a large part of the methodology.

How to use Gantt charts

Jira Software comes with two different roadmapping features, each with a slightly different focus. Jira Roadmaps is designed to track work assigned to a single team while Advanced Roadmaps is designed for larger, cross-organization project planning.

Project-specific charts - Jira Roadmaps

A screenshot of a project specific Gantt chart in Jira Roadmaps | Atlassian Agile Coach

The screenshot above, taken from Roadmaps, shows a project-specific Gantt chart that is commonly used at the team level or within a single department. The chart shows how the team is tracking toward their goals, and the collapsible work breakdown structure allows project managers to get a bird's eye view on the crucial stories of the project. Jira offers a free project management template which includes Gantt charts.

High-level organization chart - Advanced Roadmaps

Roadmaps offers quick and easy planning that helps teams better manage their dependencies and track progress on the big picture in real-time. These project or team-level roadmaps are useful for team-level planning of large pieces of work.

For planning, managing, and tracking work across multiple teams or even your entire organization, Advanced Roadmaps empower teams at scale.

Screenshot of cross-team workflow within Jira Advanced Raodmaps

Programs designed with cross-team workflows offer more advanced tools like capacity management and automatic scheduling features to help create more complex plans. They also offer a variety of view settings to allow you to customize your Gantt chart to highlight a certain aspect of your plan when presenting.

In conclusion...

Modern Gantt chart software like Jira Software with Roadmaps and Advanced Roadmaps are used by project managers and industry leaders to help organizations meet their goals. Whether planning a complex project or monitoring your company’s progress, Gantt chart tools like these are scalable and equally applicable to the portfolio, large solution, program, and team levels, as per SAFe® guidelines.

Learn more about how Roadmaps and Advanced Roadmaps can help you plan your next project. You can try them out with a free trial of Jira Software Cloud.